Tender Document Preparation:
The Steering Committee of Ken-Betwa Link Project (SC-KBLP), in its 8th meeting approved EPC tendering for the Ken-Betwa Link Canal in two packages i.e. Package-1 from Upper-Level Tunnel outlet (Beyond scope of EPC contract of Daudhan Dam) to near River Dhasan and Package-II from the River Dhasan to outfall at Barwa Sagar dam.
The tender documents for both packages after approval of Technical Advisory Group (TAG) and Tender Evaluation Committee (TEC) has been submitted to the Ministry for approval on 22-04-2026. The Government of India issued the Mother Sanction for Land Acquisition (LA) and Rehabilitation & Resettlement (R&R) on 15.06.2026. In continuation of the same, Administrative Approval was also accorded on 15.06.2026. All necessary actions related to Land Acquisition are currently under process at the administrative level.