| M1 |
Completion of Coffer Dam |
05-02-2030 |
| M2A |
Completion of Cut-off trench of Daudhan Earthen Dam |
05-04-2029 |
| M2B |
Completion of Excavation (Dam Foundation) of Daudhan Concrete Dam |
31-10-2028 |
| M3 |
Completion of Concreting line of Upper Tunnel |
05-09-2028 |
| M4 |
Completion of Excavation of Lower Tunnel |
03-11-2027 |
| M5 |
Completion of Concreting of Surge Shaft |
14-06-2028 |
| M6 |
Completion of Concreting of Daudhan Concrete Dam |
05-12-2030 |
| M7 |
Completion of Fill Placement of Daudhan Earthen Dam |
04-02-2031 |
| M8 |
Completion of Gate Installation of Daudhan Concrete Dam |
05-03-2031 |