केन-बेतवा लिंक परियोजना प्राधिकरण

Ken-Betwa Link Project Authority

Ministry Logo

1. Land Requirement - for PTR

As on 30.06.2026
Category Area (Ha)
Govt./Revenue Land 4793.36
Private Land 1223.63
Total 6017.00
Gazette Notification (IFA Sec. 29) 6017.00

2. Land Requirement for Submergence of Daudhan Dam

Component Area (Ha) Status
Forest Land 5761 Forest clearance (Stage II) granted by MoEF & CC on 03.10.2023
Government Land 1784.67 Fully mutated and transferred to WRD
Private Land 1454.33 Fully mutated and transferred to WRD
Total Submergence Area 9000.00

3. Status OF Land Acquisition (LA) Award Payment:

District Villages Affected(No.) Award amount(₹ Cr) Disbursed amount(₹ Cr) % Progress
Panna 8 92.98 84.50 90.87%
Chhatarpur 14 267.68 237.50 88.72%
Total 22 360.65 322.00 89.28%

4. Status of Abadi/Assets Award Payment

District Villages Affected (No.) Award (₹ Cr) Disbursed (₹ Cr) % Progress
Panna 7 65.05 58.93 90.59%
Chhatarpur 13 84.58 81.94 96.87%
Total 20 149.63 140.87 94.14

5. Status of R&R Award Payment Status

District Villages Affected (No.) Total PAFs (No.) Amount (₹ Cr) Total PAF's Paid Paid Amount (₹ Cr) % Progress
Panna 7+1 (Desolite) 1,321 1,65.12 1319 164.87 99.84%
Chhatarpur 14 3,718 464.75 3,494 436.75 93.97%
Total 22 5,039 629.87 2813 601.61 95.51%

6. Land Requirement for – Ken-Betwa Link Canal (Tentative)

State District No. of Villages Private Land (Ha) Government Land (Ha) Forest Land (Ha) Total
Madhya Pradesh (MP) Chhatarpur 54 873.48 187.66 90.00 1151.15
Tikamgagh 41 783.47 172.75 100.50 1056.72
Niwari 10 167.91 19.63 0.00 187.55
Uttar Pradesh (UP) Jhansi 11 182.52 13.05 3.92 199.50
Total 116 2,007.39 393.11 194.42 2594.92

Minutes of Meetings for R&R

Section 48 of the RFCTLARR Act, 2013 provides for the constitution of a National Monitoring Committee (NMC) to review and monitor Rehabilitation & Resettlement schemes.

NMC constituted on 29.08.2014.
Ken–Betwa Link Project (Phase-I) first discussed in 11th Meeting.
S.No Meeting Date Description Download
1 11th Meeting 30-10-2024 First discussion of Ken–Betwa Link Project (Phase-I) Download PDF
2 12th Meeting 30-09-2025 Review of R&R implementation progress Download PDF
3 13th Meeting 16-06-2026 Minutes of the 13th Meeting of the National Monitoring Committee(NMC) for R&R Download PDF